HCX design in VCF 9.1: site pairs, service mesh, network extension and migration types

In VCF 9.1.1 with the October 12, 2026, patches, HCX asks for two decisions. The migration type, chosen per workload and changeable between waves, sets the outage and how many VMs move at once. Network extension, chosen per network, affects every VM on it: without Mobility Optimized Networking (MON), routed traffic from migrated VMs goes back to the gateway at the source site1, ending that takes a separate network change2, and toward an NSX VPC subnet MON is not supported3. Our recommendation is Bulk where a pilot wave shows the switchover outage is acceptable, Replication Assisted vMotion (RAV) over several service meshes for live moves at volume, and plain vMotion for the few VMs that must not stop, with each extended network’s gateway move and rollback deadline fixed before its first wave.

Bulk, Replication Assisted vMotion or vMotion

Bulk migration moves VMs in parallel, can complete on a schedule and keeps the VM running at the source until failover, with an interruption equivalent to a reboot4. vMotion moves the running VM without interruption, but serially per service mesh5. RAV pairs Bulk’s parallel operations, resiliency and scheduling with a zero-downtime vMotion switchover4. Its live switchovers also run serially per service mesh, and each one ends by removing the source VM6.

Minimum bandwidth is 50 Mbps for Bulk and OS Assisted Migration (OSAM), and 150 Mbps for vMotion and RAV with WAN Optimization or 250 Mbps without. Bulk and OSAM tolerate at most 1% packet loss, the vMotion types 0.1%7.

Broadcom advises overestimating a Bulk switchover window for the checksum and instantiation, which take longer for an extremely large VM (KB 371941). By default one Interconnect (IX) appliance serves all clusters in a mesh, and additional meshes scale migration out8. KB 373010 states that with several meshes RAV switchovers can run in parallel, sequential within each mesh. When both HCX Managers run later than 9.1.0 and several meshes share the same service boundaries, HCX spreads migrations among them round robin unless a mesh is chosen9. KB 371941 suggests IX anti-affinity across hosts for this. Our recommendation is to size a large RAV wave by the switchover time per mesh, measured in a pilot.

HCX Assisted vMotion (Direct) uses native cross-vCenter vMotion, allows 50 concurrent relocations per HCX Manager, and needs a dedicated vMotion path and the same vSphere Distributed Switch version at both sites. Source VMs on NSX-backed segments are not supported10. Its minimum is 250 Mbps with a 1500-byte MTU7. OSAM brings in guests from non-vSphere hypervisors such as KVM and Hyper-V11, and its conversion halts OS services for minutes to hours, depending on VM size and activity12. Cold migration is selected automatically for powered-off VMs4.

Cutover
Minimum bandwidth
Concurrency
Bulk
Cutover: Interruption equivalent to a reboot
Minimum bandwidth: 50 Mbps
Concurrency: Parallel, the switchover can be scheduled
vMotion
Cutover: No interruption
Minimum bandwidth: 150 Mbps with WAN Optimization, 250 without
Concurrency: Serial per service mesh
Replication Assisted vMotion
Cutover: Live vMotion switchover
Minimum bandwidth: 150 Mbps with WAN Optimization, 250 without
Concurrency: Parallel replication, serial switchover per service mesh
HCX Assisted vMotion
Cutover: Native cross-vCenter vMotion
Minimum bandwidth: 250 Mbps
Concurrency: Up to 50 relocations per HCX Manager
OS Assisted Migration
Cutover: Minutes to hours of downtime for conversion
Minimum bandwidth: 50 Mbps
Concurrency: 50 active replica disks per service mesh
Figure 1. HCX migration types compared on cutover, underlay bandwidth and concurrency. Cold migration, used automatically for powered-off VMs, is left out.

What has to exist before the first wave

VCF Operations now deploys, manages, upgrades and onboards HCX Manager1314. VCF 9.1.1 shipped VCF Operations HCX 9.1.1.0, build 25690219, on September 3, 202615. The October 12, 2026, patch, 9.1.1.0100 build 25768312, adds security enhancements and is applied through VCF Operations16. Import accepts an instance at 9.1 or later, no newer than SDDC Manager, in the management vCenter or the target domain. It replaces a valid self-signed certificate with one from the management vCenter VMCA and overwrites any custom backup server with the SDDC Manager settings17.

The source site runs vSphere within Technical Guidance and always originates pairing, extensions and migrations. The destination needs NSX and a Generally Available vSphere version, and in a bidirectional installation it can also source a pair18, with its own service mesh for extensions from there11. Both sites must run the same major HCX version, and a lower minor version limits the mesh to shared features. HCX 9 is the last release to migrate legacy environments19. Coming from VCF 5.2.x, every appliance paired with an HCX already on 9.1.x must move to 9.0 or later, because 9.0 and later cannot pair with earlier versions20.

HCX registered with vCenter 9.0 or later inherits the VCF license, which covers every HCX service. Against a non-VCF vCenter, HCX runs in evaluation mode for 90 days with at most 20 migrations per type, then enters Restricted Mode unless a site in the pair is licensed21. A source HCX 9 in a legacy environment needs no license: it inherits the entitlement of its licensed HCX 9 peer inside VCF 9 for as long as that pairing lasts19.

The source initiates every connection: HCX Manager to its peer over TCP 443, the IX and Network Extension (NE) appliances over UDP 4500. Over the internet, destination public IPs go directly in the Uplink network profile, and the source may use SNAT22. Inbound DNAT, load balancing and reverse proxies are not supported in front of the tunnels7. The IX MTU, valid from 1150 to 9000, belongs in the network profile before deployment, because changing it later means redeploying the appliances and resyncing the mesh7.

Network profiles come first, then compute profiles, then the mesh, applied at the source. The IX and NE appliances are deployed only with the mesh, and NSX Manager registration is mandatory at the destination23. The destination deployment cluster must connect to the NSX transport zone22.

HCX Manager needs 4 vCPU, 12 GB memory and 60 GB disk, the IX 8 vCPU, 6 GB and 6.5 GB, the NE 8 vCPU, 3 GB and 6.5 GB, and WAN Optimization 16 vCPU, 32 GB and 172 GB. With WAN Optimization, Broadcom’s best practice is a 100% CPU and memory reservation for the IX. HA standby appliances count toward the total, and storage per appliance doubles during upgrades and redeployments8.

vCPU
Memory
Disk
HCX Manager
vCPU: 4
Memory: 12 GB
Disk: 60 GB
Interconnect (IX)
vCPU: 8
Memory: 6 GB
Disk: 6.5 GB
Network Extension (NE)
vCPU: 8
Memory: 3 GB
Disk: 6.5 GB
WAN Optimization
vCPU: 16
Memory: 32 GB
Disk: 172 GB
Figure 2. Resource requirements per HCX appliance. Storage per appliance doubles during upgrades and redeployments.

Meshes created in 9.1 use the enhanced IX and NE architecture by default, while existing appliances stay legacy unless migrated. Self-managed PhotonOS appliances are deprecated as of 9.1.0, with removal targeted for VCF 10.0.0, and WAN Optimization returns only in enhanced meshes, not for OSAM or HCX Assisted vMotion13.

With NSX at the destination, more than 8 extended networks need additional NE appliances, and with enhanced appliances more than 7 may, and the multiple-extensions-per-vNIC mode carries up to 128 extensions on one vNIC24. NE High Availability uses two appliances per site, Active/Standby without pre-emption. It survives one appliance failure and protects only the appliances, so uplink resilience needs Application Path Resiliency or multiple HCX uplinks25. The mesh’s NE count must include every planned standalone, active and standby appliance8.

Blockers that change the plan

No HCX migration supports Virtualization-Based Security4. Bulk and RAV reject virtual NVMe controllers and do not migrate snapshots, although Bulk offers to remove them626. RAV also excludes vVOL datastores, VM Encryption, independent disks and serial ports, and Fault Tolerance must be off temporarily6. vMotion needs hardware version 9 or later and excludes VM Encryption and serial ports5. Mounted ISO images block vMotion, RAV and HCX Assisted vMotion, while Bulk can force-unmount them561026. vCenter, NSX Manager and other VMware appliances cannot move with Bulk, vMotion or RAV5626. With the source vCenter and HCX Manager on 9.1.x, source ESX hosts older than 9.1 need the HBR agent for Bulk and RAV626. Snapshots during a migration, including backup snapshots, can disrupt it, so those services must stop for VMs in flight9.

HCX extends networks from distributed switches, NSX segments under the default project and NSX VPC subnets. Management and other VMkernel networks must never be extended. If NSX is registered at the source, it must be 3.2.3 or later. A destination VPC subnet accepts the Public, Private and Private Transit Gateway modes, with NSX 9.0 or later there and HCX 9.0 or later on both sites. Distributed DHCP in the source VPC service profile keeps extended VMs from the source-side DHCP server24. Extending to a distributed port group at the destination needs HCX and NSX 9.1 or later on both sites. A network reaches at most three destinations, the third only when the sites are physically co-located and traffic does not cross a WAN, and each NE appliance connects to one distributed switch or transport zone3.

HCX does not integrate with an NSX Global Manager for extension. If the registered Local Manager later joins a federation, established extensions keep working, but no new network can be extended, MON cannot be turned on or off, and extensions can be affected when their appliance is upgraded or redeployed3. A mesh with Network Extension then cannot be resynchronized until that service leaves the mesh or the Local Manager leaves the federation (KB 387390). An MTU change needs that resync, so our recommendation is to finish extension-dependent waves before federating that NSX instance.

Release 9.1.1.0 drops VMware Cloud Director as a destination, so a Cloud Director migration needs another route, and the PowerCLI module for HCX supports HCX 4.11 and no later15. Systems coming from HCX 4.11 must first remove WAN Optimization, V2T Migration and Disaster Recovery from the compute profiles and meshes of all paired appliances27.

Running and validating the waves

Mobility groups take transfer and switchover schedules for Bulk, RAV and OSAM, not for vMotion, HCX Assisted vMotion or cold migration, and Validate checks the settings before submission9. Bulk and RAV replication can run ahead of the switchover window, and RAV keeps synchronizing until the switchover begins6. Predictive estimates need at least 50 completed migrations per direction28.

A default-sized HCX Manager supports 300 concurrent Bulk and RAV migrations, at most 200 per mesh or IX. Reaching the 1,000 on the requirements page8 needs the Large form factor (16 vCPU, 48 GB memory, 300 GB storage) and the upscale configuration on the HCX Manager at both sites, (KB 373010). OSAM supports 50 active replica disks per mesh and 200 concurrent disk migrations across four meshes12.

The upgrade page asks for healthy connections to vCenter, NSX Manager and the mesh appliances, healthy site pairs, no running migrations, no new migrations or extensions planned, no failovers scheduled and a backup first29. Mesh appliances are upgraded only after the site-paired HCX Managers, and an NE upgrade disrupts extension traffic until the tunnel re-converges, in under a minute27. For the upgrade to 9.1.1.0, the release notes add that pending switchovers and new Bulk and RAV migrations can fail until the PhotonOS-based mesh is upgraded or redeployed, so Bulk and RAV work finishes first and the mesh follows the Manager immediately15. The VCF upgrade order links to the HCX Manager procedure20, run in the HCX UI or appliance management interface29, with a bundle from support.broadcom.com or VCF Operations27.

If a new Bulk VM cannot power on, it stays off and the original powers on. Without Retain MAC, the migrated VM gets a new MAC address26, while vMotion and cold migration keep it5. Our recommendation is to check which copy runs and MAC-keyed DHCP reservations. VMs using a source-side DHCP server, or static services such as DNS or NTP, can lose them once the extension is removed2.

Moving the gateway of an extended network

MON routes selectively within the destination1, with policy routes setting which traffic still uses the source gateway30. It needs a destination Tier-1 router connected to a Tier-0, extensions that terminate on a Tier-1 and VMware Tools in the VMs31. MON is not supported toward an NSX VPC subnet, an NSX VLAN segment or a distributed port group3, so on those targets routed traffic crosses the inter-site link until the gateway moves.

Moving the gateway means removing the extension, which removes the bridged layer 2 path but not the segment, port group or NSX interface. By default, the destination segment or VPC subnet stays disconnected from its gateway, to avoid a routing conflict with the source network. Selecting Connect cloud network to cloud edge gateway after unextending connects it to the Tier-1 gateway, which advertises it if dynamic routing is active. For a VPC subnet still in use at the source, Block reuse of subnet CIDR prevents inconsistent routing back to the source2. A destination VPC subnet can join its VPC gateway on removal in any access mode24.

The procedure stops at the destination. Our recommendation is to unextend only once no VM at the source needs that gateway, and to remove the source gateway interface and subnet route in the window that connects and advertises the destination network, or both sites advertise one prefix. Early unextending ends the detour, late unextending keeps the simplest rollback. If unextend fails because of the appliance state, or the source components are gone, Force Unextend removes the extension. With the on-premises site unavailable, extensions are removed from the destination NE interface so the destination router stays connected for segments hosting migrated VMs2. KB 414467 adds that destination segments can be left with gateway connectivity disabled, to be enabled by hand.

Moving an extended NSX VPC subnet’s gatewayWith the extension retained, migrated VMs at the destination route across the inter-site link to the source gateway. MON is unsupported for an NSX VPC subnet. Removing the extension removes the bridged layer 2 path. By default, the destination subnet remains disconnected from its gateway. It can connect to its destination VPC gateway on removal in any access mode, ending the detour. Once the destination network is connected and advertised, remove the source gateway interface and subnet route in the same window.1Extension retainedNSX VPC subnet: MON unsupportedMigrated VMsat destinationSourcegatewayRouted trafficInter-site link2Remove extensionBridged layer 2 path removedDestination subnet not connectedto its gateway by default3Connect destination VPC gatewayOn removal, any access modeMigrated VMsat destinationDestinationVPC gatewayRouted trafficOnce connectedand advertised4Remove source gateway interfaceand subnet routeSame window Moving an extended NSX VPC subnet’s gatewayWith the extension retained, migrated VMs at the destination route across the inter-site link to the source gateway. MON is unsupported for an NSX VPC subnet. Removing the extension removes the bridged layer 2 path. By default, the destination subnet remains disconnected from its gateway. It can connect to its destination VPC gateway on removal in any access mode, ending the detour. Once the destination network is connected and advertised, remove the source gateway interface and subnet route in the same window.1Extension retainedNSX VPC subnet: MON unsupportedMigrated VMsatdestinationSourcegatewayRouted trafficInter-site link2Remove extensionBridged layer 2 path removedDestination subnet not connectedto its gateway by default3Connect destinationVPC gatewayOn removal, any access modeMigrated VMsatdestinationDestinationVPC gatewayRouted trafficOnce connectedand advertised4Remove source gatewayinterface and subnet routeSame window
Figure 3. Removing the extension and connecting the destination VPC gateway ends the routed detour through the source.

Rollback after a wave

After a Bulk switchover, HCX keeps the renamed original in the Migrated VMs folder for recovery. The original was powered off for the final offline synchronization26, so it lacks later writes at the destination. RAV removes the source VM6 and vMotion moves the VM itself, so the way back is a reverse migration, initiated from the source in unidirectional pairing11, which needs the pair, as does a legacy source’s entitlement19. Broadcom’s HCX 9.1 guide recommends Bulk where a fast rollback is required, and warns that Upgrade Virtual Hardware and Disable HCX Per-VM EVC can prevent a move back to the legacy environment32. Once the extension and source gateway interface are gone, a returning VM has no gateway at the source.

If a failed or canceled migration does not clean up on both sites, Force Cleanup comes before Retry, because a failed cleanup can make retries fail. Retry works per mobility group, creates a new one and enables Seed Checkpoint for Bulk and RAV by default, and reuses migrated data where that option was set on the first attempt33. For the HCX upgrade, the procedure describes rolling back with snapshots of HCX Manager at both sites, and when HCX Manager runs in its registered vCenter, the workflow takes an automatic snapshot kept for one day29.

Checklist and hold criteria per wave

Our recommendation is to close each item before the step it gates. A missing item holds that step at its stopping point, and the retry needs that evidence.

  • Versions and entitlement. Owner: platform engineer. Evidence: one HCX major version at both sites, the matrix result and upgrade path for each Manager, the VCF license shown as inherited. Gates pairing. Stop: no site pair.
  • Underlay and ports. Owner: network engineer. Evidence: measured bandwidth, loss and latency against each type’s minimum, the profile MTU, the Ports and Protocols list open, no inbound DNAT or load balancer. Gates the mesh. Stop: site pair, no mesh.
  • Capacity. Owner: VI administrator. Evidence: resources with HA standby and upgrade headroom, the NE count and the KB 373010 form factor checked since the last upgrade. Gates the wave. Stop: mobility group saved, not started.
  • VM blockers. Owner: migration lead and application owners. Evidence: a per-VM blocker report for the chosen type, HBR agents on older hosts, backups paused. Gates the wave. Stop: as for capacity.
  • Extended networks. Owner: network engineer. Evidence: each network’s target type, MON setting, NSX federation status, and DHCP, DNS and NTP dependencies with their new source. Gates switchover. Stop: replication running, source VM in service.
  • Wave readiness. Owner: migration lead. Evidence: a passed Validate, the upgrade page’s health checks, no HCX upgrade or mesh redeployment before switchover. Gates switchover. Stop: as for extended networks.
  • Failed migration. Owner: migration lead. Evidence: Force Cleanup complete, the Seed Checkpoint choice and source VM state recorded. Never cancel or force-clean an OSAM migration shown Complete, which deletes the migrated VM (KB 444118). Gates Retry. Stop: the failed group untouched.
  • HCX upgrade. Owner: platform engineer. Evidence: backup and Manager snapshots at both sites, health checks passed, no migration running or scheduled, for 9.1.1.0 Bulk and RAV complete. Gates the mesh upgrade. Stop: Managers upgraded, mesh not. Retry: snapshot restored, pair healthy.
  • Rollback. Owner: application owner. Evidence: the rollback deadline, retained Bulk originals, Upgrade Virtual Hardware and Disable HCX Per-VM EVC left off, the gateway move date, and after unextend, destination gateway connectivity enabled and routing tested. Gates unextend, unpairing and deleting originals. Stop: extension and pair kept until the deadline.

Four points stay open. For the destination HCX Manager, the installation checklist says it supports load-balanced or DNAT inbound connections and elsewhere that inbound DNAT is not supported at the destination22, so a design with DNAT in front of it needs Broadcom’s confirmation first. The failed-migration page gives no source VM state after a failure, so check it in vCenter before retrying. KB 444118 covers HCX 9.1 without saying whether 9.1.1 fixes it. KB 373010 both keeps an applied form factor through upgrades and lists post-upgrade steps, so check both after each upgrade.

Sources

Show all 33 sources
  1. Understanding Network Extension with Mobility Optimized Networking
  2. Removing a Network Extension
  3. Restrictions and Limitations for Network Extension
  4. Migration Types
  5. Understanding vMotion and Cold Migration
  6. Understanding Replication Assisted vMotion
  7. Network Underlay Minimum Requirements
  8. System Requirements
  9. Migrating Virtual Machines with Mobility Groups
  10. Understanding HCX Assisted vMotion (Direct)
  11. Understanding Sites
  12. Considerations for OSAM Deployment
  13. VCF Operations
  14. Deploy VCF Operations HCX
  15. VCF Operations 9.1.1.0 Release Notes
  16. VCF Operations HCX 9.1.1.0100 Release Notes
  17. Import Existing VCF Operations HCX to a VCF Domain
  18. VCF Operations HCX Installations
  19. VCF Operations HCX Pairing Interoperability Policy
  20. Upgrading to VMware Cloud Foundation 9.1.x
  21. About Licensing
  22. Preparing for General Installation
  23. About the Service Mesh
  24. Requirements for Network Extension
  25. Understanding Network Extension High Availability
  26. Understanding Bulk Migration
  27. Planning for VCF Operations HCX Upgrades or Patches
  28. Estimate Migrations with Mobility Groups
  29. Upgrade HCX Manager to 9.1.x
  30. Mobility Optimized Networking Policy Routes
  31. Requirements and Limitations for Mobility Optimized Networking Topologies
  32. The Complete Guide to Workload Mobility with VMware Cloud Foundation Operations HCX 9.1 (Part 3: Extending Networks and Migrating Workloads)
  33. Managing Failed or Canceled Migrations