A provider leaving VMware Cloud Director (VCD) for VMware Cloud Foundation 9.1.1, with its October 12, 2026, patches, has two documented routes into VCF Automation. The Migration Tool, new in VCF Automation 9.1, performs an in-place migration1 that carries organizations, Provider VDCs, organization VDCs, vApps and VMs2 and the edge gateway firewall rules3 across. HCX moves only the VMs, from the vCenter behind VCD over a vCenter-to-vCenter connection that bypasses VCD (KB 442369).
Broadcom fixes the source of the Migration Tool path at VCD 10.6.2, which it calls the hardened baseline for the move4. That release is dated September 3, 2026, with build 25707817 and installed build 257051865. The target builds chosen here are VCF Automation 9.1.1.02006 and Migration Service Engine 9.1.1.02007, both released on October 12, 2026, under build 25801570. The full migration guide is not on TechDocs. Broadcom sends it on request once the Environment Assessment Tool (EAT) has run4.
Our recommendation is to choose the route per tenant before any upgrade work starts, and to plan the runbook around its last go or no-go point: after an organization’s regional migration has been validated and before its first VM moves. Up to that point the documented rollback applies. After it, the cited pages describe no return to VCD.
Migration Tool or HCX
Broadcom describes the Migration Tool as a fully supported, documented, UI-based and tool-assisted path once VCD is on 10.6.24, and the 9.1 What’s New refers readers to their Broadcom representative for details1. For the VMs themselves, the Supervisor release notes say the VCD migration tool or the API can import them onto the Supervisor without disruption, in batches with a defined order, with rollback while the operation is in progress8.
The HCX route exists because HCX 9.x does not integrate with VCD instances. KB 442369 deploys HCX 9.1 at both sites, registers the source HCX directly with the vCenter 8.x behind VCD and migrates the VMs into a namespace. VCF Operations HCX 9.1.1.0 no longer offers VCD as a destination9. The KB is written for VCD 10.6.x in general and does not mention the 10.6.2 baseline. The HCX design guide for VCF 9.1 covers the HCX side.
None of the cited Broadcom pages compares the two routes, so our recommendation follows from what each one moves. HCX bypasses VCD, which means organizations, quotas and firewall rules do not travel with the VMs and must already exist in VCF Automation when the VMs land. The Migration Tool suits tenants that should arrive with that structure intact. HCX fits a tenant whose VCD constructs are simple enough to rebuild by hand, or one the Migration Tool cannot take, such as Provider VDCs caught by the multi-vCenter limit described under the target design.
Source and target builds, and the order between them
VCD 10.6.2 upgrades from any earlier 10.6.x release: 10.6.0, 10.6.0.1, 10.6.1, 10.6.1.1 or 10.6.1.2. It adds support for VCF 9.1.1, alongside vSphere 9.1.1 and NSX 9.1.1. The upgrade fails when the SAN of the PostgreSQL certificate lacks the database IP address, which appliances on the default self-signed PostgreSQL certificates already have. The VCD management packs and content packs for Operations available today are incompatible with 10.6.2, and the release notes tell a provider that relies on them to find another monitoring option before upgrading5.
Extensions narrow the step further. VCD 10.6.2 shares its end-of-life date with VCF 9.1, and the Container Service, Data Solutions and Object Storage extensions are supported on request only (RPQ)4. VMware Cloud Director Availability is fully supported, and in the release notes’ own words VMware Cloud Foundation supports only the extensions that the 10.6.1.2 release notes list5. Our recommendation is to get Broadcom’s RPQ answer for each such extension in use before committing to 10.6.2.
On the VCF side, upgrading VCF Operations to 9.1.1 with VCD 10.6.2 means deploying a VCF 9 fleet, and the release notes ask the design to account for a strict 1:1 relationship between VCF Operations and VCF Automation5. The migration service engine is one of the components that fleet lifecycle installs, upgrades, patches, backs up and restores10. Engine 9.1.1 needs database capabilities that only VCF Automation 9.1.1 delivers11. KB 455559 reports the blocked patch that the reverse order caused, including through the Upgrade All option, as resolved in the 9.1.1.0100 patch, and the Resolved Issues section of the 9.1.1.0200 notes still says the engine upgrade follows the completed VCF Automation upgrade6.
The EAT runs on a VCD cell against VCD 10.4.x, 10.5.x or 10.6.x and writes a human-readable Excel report, with no telemetry or automatic upload, and the provider controls what is sent12. Broadcom’s sequence has three steps: run the EAT and send the report, with a fresh submission encouraged when the last one is more than six months old, request the migration documentation from the same Broadcom mailbox, then connect the VCF Automation Migration Service to VCD4.
Firewall blockers to clear before the window
Broadcom makes an audit of every VCD edge gateway rule mandatory before the migration starts13. Only centralized Tier-1 edge gateways with an active firewall qualify, and gateways deployed in distributed-only mode are skipped entirely. Rules created directly in NSX Manager are invisible to the tool. A rule passes with IPv4 addresses, IPSet groups, default services and the L4 protocols TCP and UDP, while a rule with IPv6 addresses causes the whole gateway to be skipped13. MAC sets, user-defined application port profiles, network context profiles and a specific “applied to” value have to be changed in VCD first. Distributed firewall rules are bypassed, because they depend on VCD constructs that are not migrated14. On a gateway whose firewall is disabled, the security configuration update and every later step for that gateway are skipped3.
Each gateway is all or nothing. One unsupported rule rejects the firewall migration for the whole gateway, which avoids a partial security posture14. The IPSet groups the rules use must already be migrated to VCF Automation Network Security Groups, and an incomplete IPSet mapping in the plan fails every rule that references those groups, which can trigger the same rejection15. Whether the new policy is stateful follows the stateful property of the NSX Edge cluster behind the VCD gateway3.
The evaluation can run on provider infrastructure, an organization or workloads, and it shows what will be migrated or skipped before anything changes13. Our recommendation is to run it on each organization while the source is still in production, weeks before its window, so the exclusions become a cleanup list per gateway that the tenant can agree to.
Target design: regions, quotas and VPCs
The metadata table in the VCF Automation API guide shows where each VCD entity goes. An organization stays an organization and is migrated by its VCD organization ID. A Provider VDC becomes a region, an organization VDC a region quota, a vApp a namespace, and a VM a VM Service VM. Provider metadata on vApps and VMs lands on the region quota, while tenant metadata follows the namespace or the VM2.
On the network side, the vDefend Firewall 9.1 guide maps each VCD edge gateway to a transit gateway (TGW), and the migration plan records which one. The edge gateway firewall rules move entirely to the TGW rather than a VPC gateway15, as a newly created TGW firewall policy3. At cutover, VMs leave the VCD networks for the new VPC subnets16.
Every target in that list belongs to the All Apps side of VCF Automation, the side with namespaces, region quotas, VM Service and VPCs, which the VCF Automation design guide for 9.1 describes.
Because Provider VDCs become regions, the region design has to fit the Provider VDCs being migrated. A region is one or more Supervisors that share an NSX Local Manager, all clusters and zones of a Supervisor must be managed by the same vCenter, and a region that spans several workload domains shares one NSX Local Manager across them. The design library uses separate regions where greater scale or physical separation is needed, and a namespace is scoped to a single region17. The source layout has a limit of its own. KB 451182 states that the Migration Tool in VCF Automation 9.1 cannot migrate Provider VDCs on one NSX-T Manager that are backed by several vCenter Servers. Two Provider VDCs that each use a single vCenter can therefore still hit the limit when they share an NSX-T Manager. Our recommendation is to group the Provider VDCs by NSX-T Manager and list every vCenter behind each group before the region plan is drawn up. The provider also chooses which VM classes and storage classes an organization may use when it creates each region quota17.
Every new organization gets a default VPC and inherits the default private TGW and VPC IP blocks, which can be customized for that organization in its regional network configuration. External connections are either centralized, through an NSX Tier-0 or Tier-0 VRF with NAT, load balancing, IPsec VPN and gateway firewall available inside the organization, or distributed VLAN connections that need no Tier-018.
Tenants map namespaces to VPCs, one VPC per namespace or one VPC shared by several, with separate VPCs where workloads need segregation18. Since each vApp becomes a namespace2, a tenant with many vApps ends up with many namespaces, and its namespace-to-VPC choice then sets how many VPCs follow.
Order of the migration
The administrator logs in to the VCF Automation UI as a service provider and opens VCF Services > Migration Tool. The regional procedure starts there with a Sync on the target organization, so that the migrator matches the current VCD state, before the provider infrastructure is migrated3.
Provider Infrastructure Migration, which moves the provider (Tier-0) gateway components, has to finish first. Organization Infrastructure Migration moves the organization’s networking components and creates its VPC and TGW structures. It is the main prerequisite for the firewall, and the tool must show it as done before Organization Regional Migration starts15. For each edge gateway, the regional phase updates the security configuration, then copies the default rule action, then migrates the user-defined rules, and several selected gateways are migrated one after another3. When the evaluation or a migration run finds a violation, the rules are fixed in VCD and the plan is generated again until every edge gateway sub-module shows Completed rather than Skipped or Rejected13. Workloads move only after that, so the TGW policies apply as soon as the VMs connect, though group membership can take some time to re-evaluate16.
Readiness checklist
Broadcom documents the requirements. The roles and the evidence are our recommendation.
- Migration lead, assessment and guide. Evidence: an EAT report submitted less than six months before the window and the migration documentation received from Broadcom4.
- VCD administrator, source build. Evidence: every cell on VCD 10.6.2, installed build 25705186, and before that upgrade a PostgreSQL certificate whose SAN contains the database IP address5.
- Service owner, extensions and monitoring. Evidence: Broadcom’s written RPQ answer for each Container Service, Data Solutions or Object Storage extension in use4, and a monitoring option in place of the VCD management and content packs5.
- VCF lifecycle administrator, target builds. Evidence: VCF Automation 9.1.1.0200 upgraded first6 and Migration Service Engine 9.1.1.02007 afterward, after a backup of both in fleet lifecycle10, and as two separate tasks rather than
Upgrade All. - Provider architect, region plan. Evidence: the Provider VDCs grouped by NSX-T Manager, with each group backed by a single vCenter Server or routed elsewhere (KB 451182), one VCF Automation per VCF Operations5, and region quotas with their VM classes and storage classes17.
- Network and security owner, per gateway. Evidence: an evaluation run on the organization in which every in-scope gateway is centralized, has its firewall active, carries only supported rule content and has every IPSet group mapped to a Network Security Group in the plan1315. Gateways left out need an approved exception with a replacement design, not a hasty change to production security.
- Tenant service owner, tests beyond the firewall. Evidence: a signed test plan per organization for NAT, VPN and application reachability, since the cited pages validate only the firewall16.
Hold criteria, the safe stopping point and retries
After the Organization Regional Migration, a clean edge gateway shows the Security Configuration Update, Default Rule Update and User-Defined Rule Migration sub-steps as Completed. A rule that cannot move is marked Skip, with an alert naming the reason: a disabled VCD firewall, an unsupported protocol, or a gateway deployed in distributed-only mode. The Manage & Govern tab in VCF Automation should then show the VCD firewall rules on the specific gateway they were migrated to16, and the new TGW firewall policy should carry the same stateful or stateless setting as the NSX Edge cluster behind the VCD gateway3. When something fails, the plan shows the previous and new state of each rule and the step it stopped in, and the migrator server logs hold the detail14.
Rollback is started from the VCF Automation organization portal on a regional migration that has completed or partially failed. It covers the whole organization and runs in reverse: the new TGW firewall policy is deleted, then the default rule action and the security configuration are reverted. Success means the edge gateway and the region are gone from VCF Automation, no firewall policies remain under that gateway, and the organization infrastructure matches its state before the infrastructure migration19. Apart from the in-progress VM import rollback8, none of the cited pages covers a return to VCD after workloads have moved.
Until Broadcom’s migration guide says otherwise, our recommendation is to treat the interval between a validated regional migration and the first VM move as the safe stopping point. Our hold criteria, each a reason to stop:
- Before the window: any checklist item above without its evidence.
- During the platform patch: VCF Automation not yet at 9.1.1.0200. Hold the migration service engine upgrade.
- During the migration: Provider or Organization Infrastructure Migration not marked done15. Hold the regional phase.
- Before cutover: any edge gateway sub-module
SkippedorRejectedwithout an approved exception, a TGW firewall policy missing fromManage & Govern, or a stateful setting that differs from the source NSX Edge cluster316. Hold that organization’s workloads at the safe stopping point. - After the first VMs move: a failed reachability or application test from the tenant plan. Stop further waves and open a Broadcom Support case, since the cited pages describe no return to VCD after VMs have moved.
Our recommendation is to retry only on named evidence. A rejected gateway is retried after its rules are fixed in VCD and the regenerated plan shows all three sub-steps migrated for that gateway14. For the blocked patch that KB 455559 describes, the remediation on the VCF Automation appliance has to report success first. Only then is the VCF Automation upgrade retried, with its backup precheck passing, and the migration service engine after that upgrade finishes. After a rollback, the next attempt starts with the rollback’s own success checks, a fresh Sync on the organization3 and a new evaluation whose only Skipped or Rejected results are approved exceptions13.
What the public pages don’t answer
Three points here are inferred. The migration service engine is taken to be what runs behind the Migration Tool UI, because the firewall chapter speaks of the migrator and its logs14 and KB 455559 calls the engine VCD Migrator. A migrated tenant is taken to land in an All Apps organization, because every target object belongs to that side, and centralized connections are taken as the landing point for external networking, because the first phase moves Tier-0 components. The pages also leave open how catalogs, vApp templates, users, identity providers and storage policies migrate, what happens to NAT, VPN, load balancing, routing and organization VDC and vApp networks, and whether a distributed VLAN target is supported. Our recommendation is to put these questions in the guide request and get Broadcom’s answers before approving the target design or the migration runbook.
Sources
Show all 19 sources
- VCF Automation
- Metadata Management
- Migrate VCD Edge Gateway Firewall
- Announcing VMware Cloud Director 10.6.2, Enabling Your Migration to VMware Cloud Foundation 9.1 (VMware Cloud Provider Blog, September 3, 2026, archived copy)
- VMware Cloud Director 10.6.2 Release Notes
- VCF Automation 9.1.1.0200 Release Notes
- Migration Service Engine 9.1.1.0200 Release Notes
- VMware vSphere Supervisor Release Notes
- VCF Operations 9.1.1.0 Release Notes
- VCF Operations
- VCF Automation 9.1.1.0 Release Notes
- EAT – The VMware Cloud Director Environment Assessment Tool (VMware Cloud Provider Blog, June 2, 2025, archived copy)
- Auditing and Remediation Workflow
- Troubleshooting and Maintenance
- Prerequisites and Dependencies
- Validate Post-Migration and Workload Transition
- Understanding Supervisors, Regions, vSphere Zones, vSphere Namespaces, & Classes