Sizing a workload domain in VMware Cloud Foundation 9.1.1, with the October 12, 2026, patches, means finding capacity in two places. The domain’s own clusters must carry the workloads plus a reserve for host failures. The management domain must also find room for the domain’s vCenter and, unless the domain shares one, its NSX Manager. For a newly deployed workload domain, VCF deploys both on the management domain’s primary cluster1, so that share never shows on the new domain’s hosts.
Approving a new domain comes down to four figures: the room left in the management domain’s primary cluster after its failover reserve, the vCenter size, the NSX Manager node count and size, and each cluster’s host count. Our recommendation is to settle the management domain figure first, size vCenter for the planning horizon and resize later, give a domain its own three-node NSX Manager unless it is upgraded together with the domains it would share with, and start each single-site cluster at four hosts.
What the management domain carries for each domain
The placement holds even for a domain created with the “domain infrastructure only” option, which has no vSphere cluster: its vCenter and NSX Manager still land in the management domain, and no unassigned hosts are needed1. Broadcom’s management domain design requires sizing it for the workload domains and management components you plan to add, though its hardware may not be fully used until that scale2. The documented ceiling is 40 workload domains per VCF Instance3. Every one would place its vCenter in the same management cluster, so our recommendation is to plan against that cluster’s capacity rather than the limit.
What is already there depends on the VCF Installer profile chosen at deployment: Simple, or High Availability Small, Medium or Large. For the fleet’s first VCF Instance, the management domain vCenter is Small in Simple and HA Small, Medium in HA Medium and Large in HA Large. NSX runs as one Medium node in Simple, three Medium nodes in HA Small and HA Medium, and three Large nodes in HA Large. Broadcom totals Simple at 76 vCPU, 251 GB of memory and 7,448 GB of disk, HA Small at 106 vCPU, 335 GB and 8,422 GB, HA Medium at 184 vCPU, 656 GB and 11,445 GB, and HA Large at 298 vCPU, 949 GB and 15,357 GB. These are the 9.1.1 profiles, since 9.1 does not support HA on a Small deployment (KB 452952). Additional-instance profiles list no VCF Operations, VCF Automation or license server and start at 34 vCPU, 111 GB and 4,562 GB in Simple. Log Management, a Day-2 option, upscales every management services worker node to Large or xLarge when it is deployed4. None of these totals includes a workload domain vCenter or NSX Manager, so add those appliances.
The sum has to fit after a host failure. The cluster model puts a High Availability management domain default cluster at four hosts with 25% of CPU and memory reserved, and a Simple one on vSAN at three hosts with 33%5. Broadcom’s 9.1.1 Planning and Preparation Workbook takes one row per workload domain on its Management Domain Sizing sheet, with the vCenter size, vCenter storage size, NSX model and NSX size, and reports CPU, memory and disk per host on N-1 hosts6. In our arithmetic, a workload domain with a Medium vCenter on default storage and its own three-node Medium NSX Manager adds 26 vCPU, 102 GB of memory and 1,833 GB of disk to the management domain678.
In 9.1.1, VCF management services need less compute and memory at every deployment size, and the VCF Installer defaults to small instead of medium. The release notes call small fully capable and optimized for production environments that require high availability, and refer to the workbook for sizing details9. In 9.1, enabling HA on a Small deployment by any method leaves the system unsupported and unrecoverable, and Broadcom says to plan a scale-up to Medium where HA is required. The limit no longer applies from 9.1.1.0 (KB 452952). For environments patched to 9.1.1, they point to a footprint reduction article (KB 455842)9. The KB applies once all components run 9.1.1, and only to a management services cluster that hosts the Day 0 components alone, without Log Management and Real-time Metrics. Its script replaces the worker nodes, which can disrupt operations, so Broadcom says to run it in a maintenance window. Our recommendation is to recalculate the management sums after the rollout, before giving what it frees to the next domain.
Sharing an NSX Manager or deploying one
Joining an existing NSX Manager instance adds no NSX appliances to the management domain, though the shared instance may need a larger size. A domain that gets its own adds up to three. In 9.1 the instance it joins can be the management domain’s own. A new instance is either a single node (Simple), which needs fewer resources, or a three-node cluster (High Availability), which Broadcom recommends because it keeps the management and control plane available and minimizes downtime during upgrades1. The appliance size is Medium, Large or Extra Large, and the design tells you to check VMware Configuration Maximums for the form factor your scale needs110. A three-node cluster runs in the management domain’s default cluster, its nodes kept apart by an anti-affinity rule, and the design asks for at least four hosts there so that all three keep running after a host failure10.
The workbook gives each form factor’s per-node size and supported scale, and lists a further Small size for proofs of concept only6.
- Medium: 6 vCPU, 24 GB of memory and 300 GB of disk per node, so 18 vCPU, 72 GB and 900 GB for three nodes. Up to 128 hosts and 5 vSphere clusters.
- Large: 12 vCPU, 48 GB and 300 GB per node, so 36 vCPU, 144 GB and 900 GB for three. Up to 1,024 hosts and 256 vSphere clusters.
- Extra Large: 24 vCPU, 96 GB and 400 GB per node, so 72 vCPU, 288 GB and 1,200 GB for three. Up to 2,048 hosts and 512 vSphere clusters.
On a shared NSX Manager, every cluster in the attached domains counts against one instance, and Medium allows five. With clusters averaging under about 26 hosts, the cluster count runs out before the 128 hosts. Our recommendation is to size a shared instance for every cluster that may ever attach across its domains, and to make it Large if that could exceed five clusters or 128 hosts.
Sharing ties the domains to one instance’s limits, upgrades and failures3. A dedicated Medium cluster takes 18 vCPU, 72 GB and 900 GB in the management domain, and Simple a third of that, without the availability Broadcom cites for three nodes. Our recommendation is a dedicated three-node instance for any domain with its own upgrade schedule or failure tolerance. The NSX design article sets out which domains can share an instance.
Choosing the vCenter size
vSphere 9.1 defines the vCenter appliance sizes by inventory: Tiny for up to 10 hosts or 100 virtual machines, Small for 100 or 1,000, Medium for 400 or 4,000, Large for 1,000 or 10,000 and X-Large for 2,000 or 35,000. Tiny takes 2 vCPU and 14 GB of memory, Small 4 vCPU and 21 GB, Medium 8 vCPU and 30 GB, Large 16 vCPU and 39 GB, and X-Large 24 vCPU and 58 GB. Storage is chosen separately7. Host count is not the only trigger: a host with more than 512 LUNs and 2,048 paths needs a Large or X-Large appliance7. In a Fibre Channel domain with many LUNs, that rule can set the size first.
The workload domain wizard in VCF Operations asks only for the vCenter’s FQDN, IP address and gateway, with no appliance or storage size1. The storage figures still belong in the management domain sum, as they show how much disk a domain’s vCenter can claim. With the default storage size, vSphere 9.1 lists 734 GB for a Small appliance, 933 GB for a Medium and 1,383 GB for a Large. The Large storage option raises every appliance size to between 2,059 and 2,408 GB, and X-Large storage to between 4,319 and 4,668 GB, which also lets an X-Large appliance manage up to 2,500 hosts or 45,000 virtual machines. It also depends on the disk provisioning mode, and it includes vSphere Lifecycle Manager, which runs as a service inside the appliance8. In VCF that growth comes through the resize described next, so our recommendation is to keep free disk in the management domain for the size each domain may reach.
vCenter 9.1 has a resize API that scales up compute and disk with a single API call and a reboot. The API resize is not supported while the vCenter runs on snapshots and should follow a backup, and unless deferred, its service restart drops vSphere Client connections. Resizing is one-way: you cannot reduce the vCenter size or its disks afterward11. Growing an undersized vCenter therefore takes a reboot, while an oversized one keeps its footprint in the management domain for good. Our recommendation is to size for the inventory expected within the planning horizon and resize when the domain outgrows it.
Minimum hosts per cluster and the failover reserve
Inside the domain, the minimum depends on principal storage. A workload domain cluster on vSAN (OSA or ESA) needs at least three hosts and, with the recommended admission control, reserves 33% of its CPU and memory to tolerate one host failure. A cluster on NFS or Fibre Channel needs at least two hosts and, on the same basis, reserves 50%5. Both percentages follow the recommended admission control, set for one host failure with percentage-based failover capacity that vSphere calculates from the host count, so four hosts give the resources of three5.
Four hosts is where each storage design page recommends starting121314. On vSAN, a three-node cluster tolerates one host failure but will not rebuild components automatically afterward, while four nodes allow automatic rebuild and Reserved Capacity512. In a two-host NFS or Fibre Channel cluster, losing one host to a failure or maintenance doubles the CPU commitment ratio, to 2:1 in Broadcom’s example1314.
The storage pages’ Simple-install remark concerns only the management domain default cluster, four hosts in a High Availability install5121314.
A stretched vSAN cluster in a workload domain needs at least six hosts, and the stretched cluster model gives no recommended start for it. Stretched NFS or Fibre Channel needs one host per site at minimum, with two per site recommended. Broadcom recommends raising admission control to half the hosts, so that all virtual machines still have resources after an availability zone outage, which leaves an eight-host stretched cluster with the resources of four15. Stretching a workload domain cluster can also add hosts and a witness to the management domain, and the vSAN stretched cluster design counts them.
In a cluster with Memory Tiering, vCenter 9.1.1 has HA admission control track DRAM as a separate resource next to total memory, so that a failover cannot fail silently for lack of DRAM16.
vSAN capacity beyond the host count
On vSAN, the host count also sets how much raw capacity you hold back. The design recommends enabling Reserved Capacity, whose Host Rebuild Reserve shrinks as the cluster grows, and suggests host counts large enough to bring the reserve percentage down, from 25% at four nodes to 8% at twelve12. The reserve is not supported on three-node clusters, stretched clusters or clusters with fault domains12. In those designs the failure capacity is yours to budget.
In a single-site ESA cluster, the Auto-RAID policy sets the layout by host count: RAID-5 (2+1) with one failure to tolerate on three to five hosts, and RAID-6 (4+2) with two failures from six hosts, both at 1.5 times the protected data17. Broadcom’s vSAN FAQ calls Host Rebuild Reserve and Operations Reserve pre-9.1 constructs, no longer relevant with Auto-RAID and the Effective Capacity view18. By our reading, RAID-6 (4+2) on six hosts leaves none to rebuild on. Our recommendation is four or five hosts where RAID-5 is enough, and seven where RAID-6 has to survive a host that stays out for days.
vSAN ESA requires at least 16 cores and 128 GB of memory per node, the figures for the smallest ReadyNode profiles, and drives of at least 1.6 TB, with up to 24 drives per node. The page warns that fewer cores per node can mean more nodes for the same workload12. vSAN OSA needs at least one disk group per node, and the design recommends two, which means two cache devices that add no capacity19. For the capacity sums, both pages point to the workbook1219.
Checklist and hold criteria
- Management domain capacity. Owner: virtualization architect. Evidence: the workbook’s Management Domain Sizing sheet with a row for every existing and planned workload domain, per-host CPU, memory and disk on N-1 hosts within what the hosts provide, and the remaining room recorded for the next domain.
- Management services footprint. Owner: platform operations lead. Evidence: the deployment profile and size recorded, plans for Log Management and Real-time Metrics, no HA forced on a Small 9.1 deployment, and where a KB 455842 rollout is planned, its completion in a maintenance window.
- vCenter size. Owner: VI administrator. Evidence: the forecast hosts and virtual machines for the planning horizon against the size table, LUN and path counts per host in Fibre Channel domains, and the storage size the forecast may need.
- NSX Manager. Owner: network architect. Evidence: the shared or dedicated decision with its upgrade group and accepted failure domain, node count and size against the cluster and host limits of every domain that may attach, and four or more hosts in the management default cluster for three nodes.
- Cluster host counts. Owner: virtualization architect. Evidence: per cluster the principal storage and host count against Figure 2, three or more wherever admission control runs, exported HA admission control settings (one host failure and percentage-based, or half the hosts when stretched), and for tiered clusters the reserve checked against DRAM.
- vSAN capacity. Owner: storage architect. Evidence: ESA nodes at 16 cores, 128 GB and drives of 1.6 TB or more, the OSA disk group layout, Auto-RAID or Reserved Capacity recorded per cluster, and the workbook capacity sum.
Our recommendation is to hold the workload domain wizard while any of the first four items, or the planned host counts and vSAN hardware of the last two, lacks its evidence or fails. The safe stopping point is hosts commissioned and the wizard unsubmitted. A retry needs the missing record or the fix: the sizing sheet within capacity on N-1 hosts after the management domain is expanded or rightsized, a KB 455842 rollout whose platform package deployment reports Successful, a Small 9.1 deployment scaled up to Medium or patched to 9.1.1.0, a Large or X-Large vCenter budgeted where LUN and path counts require it, four hosts in the management default cluster or a dedicated or Large NSX instance where a shared Medium one would exceed five clusters or 128 hosts, hosts commissioned up to the Figure 2 count and at least three where admission control runs, or a corrected bill of materials for ESA nodes under 16 cores, 128 GB or 1.6 TB drives.
Production workloads wait for the rest of the last two items: admission control settings exported, the DRAM check done and the policy state recorded per cluster, plus the deployed vCenter size checked against its record. The stopping point is the deployed domain without production workloads. A retry needs those records, with admission control matching the cluster model on at least three hosts, the capacity sum within the hosts and an undersized vCenter resized up.
Some points stay open, each with our conservative action. The cluster model sizes NFS and Fibre Channel clusters from two hosts with 50% reserved, while the vSphere HA documentation says admission control needs at least three hosts520: plan three wherever admission control runs. The vSAN design pages recommend Reserved Capacity while the vSAN FAQ sets it aside under Auto-RAID1218: use Auto-RAID with Effective Capacity on ESA, and Reserved Capacity only where Auto-RAID is not used and it is supported. The wizard offers no vCenter size while the workbook sizes each domain’s vCenter16, and no cited page says which size the wizard deploys: budget for the forecast size and check the deployed one.
A short workload domain can take another host. A management cluster without room for another vCenter or a three-node NSX Manager blocks the next domain until it is expanded, so our recommendation is to check that remaining figure before each new domain is approved.
Sources
Show all 20 sources
- Create a New Workload Domain
- Management Domain Model
- VCF Domain Models
- VCF Fleet Sizing Models
- Single-Rack vSphere Cluster Model
- VMware Cloud Foundation 9.1.1 Planning and Preparation Workbook
- Hardware Requirements for the vCenter Appliance
- Storage Requirements for the vCenter Appliance
- VCF Installer / SDDC Manager 9.1.1.0 Release Notes
- High Availability NSX Manager Model
- Resizing VMware vCenter in VMware Cloud Foundation 9
- Single-Rack vSAN ESA Storage Model
- NFS Storage Model
- Fibre Channel Storage Model
- Stretched vSphere Cluster Model
- vCenter 9.1.1.0 Release Notes
- Selecting the Best RAID Configuration for a vSAN Storage Cluster
- vSAN Frequently Asked Questions
- Single-Rack vSAN OSA Storage Model
- vSphere HA Admission Control