When a new group of workloads arrives and someone asks for “its own environment”, VMware Cloud Foundation 9.1.1, with the October 12, 2026, patches, offers three answers: another vSphere cluster in an existing workload domain, a new workload domain or a new VCF Instance.

Our recommendation is to add a cluster when the workloads need only capacity or a separate rack or availability boundary, and to create a workload domain when they need their own vCenter or NSX authority, identity provider, upgrade schedule, network change control or compliance scope, or have networks managed outside VCF Automation. Move up to another VCF Instance only when instance-level management must fail independently or disaster recovery must reach another region. A new domain gets a dedicated NSX Manager when its network administration or upgrade timing must be separate, and otherwise joins an existing one, which Broadcom’s design also uses when a VCF Automation region spans the domains.

Fleet, instance and domain in VCF 9.1

A VCF fleet holds one or more VCF Instances, and its fleet-level components, VCF Operations and VCF Automation, run in the management domain of the first instance. Each instance consists of a management domain and, optionally, workload domains1, so a workload domain belongs to one instance, as the multi-site design article describes for a second site.

Inside the instance, a domain is one vCenter instance with one or more vSphere clusters running vSphere HA and DRS. Each cluster has at least one vSphere Distributed Switch for system traffic, with NSX segments for workloads, and the domain has shared storage and one NSX Manager instance, either dedicated to it or shared with other domains. For the first workload domain, VCF Operations deploys a vCenter instance in the management domain and, if your organization requires one, an NSX Manager instance, and each further workload domain adds another vCenter there. Where several existing vCenter instances have been converged to VCF, management components can also sit in workload domain clusters1. For a newly deployed workload domain, the vCenter and NSX Manager land on the management domain’s primary cluster2.

Another cluster in an existing domain

The lightest option, a new cluster in an existing workload domain, brings new hosts, new capacity and, if needed, a separate rack or availability boundary: VCF 9.1 describes single-rack, layer 2 multi-rack, layer 3 multi-rack and stretched cluster models, and one workload domain can contain a combination of them3. The cluster shares the domain’s vCenter, single sign-on domain and NSX Manager, and every upgrade of those components. That suits workloads with the same administrators, security policy, network change control and maintenance windows as the domain. In Broadcom’s design a Supervisor can have several vSphere Zones, each mapped to a cluster, and all of them must be managed by the same vCenter4. Our reading is that a new cluster can serve an existing Supervisor, while a new domain, with its own vCenter, cannot.

From 9.1.1, generally available since September 3, 20265, clusters in a VCF domain can share one distributed switch in greenfield deployments6, and the NSX 9.1.1 release notes credit it with less provisioning work and consistent configuration and policies across clusters7. The workload domain procedure adds that the first cluster of a new domain cannot share a switch, because none exists yet to reuse, while clusters added later can share the first cluster’s switch2. Our recommendation is to join the domain’s switch only with a cluster added purely for capacity. A cluster with a different NIC layout or its own change window is easier to keep on a switch of its own, because MTU, the number of uplinks and the LAG settings belong to the switch, while only the mapping of uplinks to physical NICs is set per host2, and a change to the switch reaches every cluster on it.

What a new workload domain adds

Broadcom documents a new workload domain as running on dedicated ESX hosts, with its own vCenter and vCenter Single Sign-On domain, support for configurations with a dedicated identity provider and independent lifecycle management. VCF Instances upgraded from an earlier version may have shared Single Sign-On domains8. The documented ceiling rose from 24 workload domains per VCF Instance in 9.09 to 40 in 9.18. A new domain needs additional hardware for its own hosts8 and one more vCenter to patch in the management domain, whose credentials, certificates and upgrade plans need an owner on the change calendar. Broadcom also notes that the management domain may need more resources to accommodate future workload domains and additional management components8. Our recommendation is to expand the management domain before deploying the new domain whenever that room is missing. The workload domain sizing article has the appliance sizes for that sum.

Broadcom’s tenancy design describes a dedicated workload domain per organization under a shared management domain, and lists its best fits: multi-tenant service providers, separate business divisions, regulated industries, organizations handling sensitive information, performance-sensitive workloads, specialized hardware such as GPUs, data sovereignty, and mergers or acquisitions10. Where VCF Automation is in use, the centralized connectivity design states that mixing another network consumption vehicle in the same workload domain is not recommended in general, naming VPCs configured through the vCenter UI in the Default Project11. Our recommendation is a separate workload domain for workloads whose networks are managed outside VCF Automation, and the VCF Automation design applies the same caution to All Apps and VM Apps organizations sharing a domain under Mixed Tenancy Mode.

Shared or dedicated NSX Manager

A new workload domain can share the NSX Manager cluster of an existing workload domain or of the management domain, or you can deploy a new NSX Manager cluster1. Sharing the management domain’s manager is new in 9.1: the 9.0 documentation stated that workload domains cannot use the management domain’s NSX Manager cluster12. Domains that share an NSX instance can also share its NSX Edge clusters8.

Domains on a shared NSX instance also share its failures and its upgrades: a failure has a larger blast radius, and upgrades and patching affect every domain on it8. Under the lifecycle documentation, the NSX, vCenter and ESX components must be upgraded in all domains that share the instance, and canceling the automatically created upgrade plan of one dependent domain cancels it for all of them. When the shared instance is the management domain’s, the NSX Manager node upgrade, the NSX Edge cluster upgrade and the NSX upgrade finalize step are started from the management domain only13.

If the shared instance was deployed in an IPv4-only VCF domain, the new domain must use IPv4 between its components even when it is configured for dual-stack. On an NSX 9.1 instance, a domain whose vCenter runs 9.0.x or 8.0.x stays in a pinned state limited to that vCenter’s features, and new NSX 9.1 features remain inactive until the ESX hosts of all attached workload domains are upgraded. From 9.1.1, a domain that joins shares the full stack VPC with every full stack VPC or NSX TEP-configured domain on the instance2. For a VCF Automation region that spans several workload domains, Broadcom’s design shares one NSX Local Manager across all of them4. The NSX design article adds the scale limits of a shared instance and the VLAN-backed VPC case.

A dedicated NSX Manager removes the shared-instance upgrade dependency and gives the domain separate network management. Broadcom lists a higher footprint as the implication8: another NSX Manager cluster in the management domain. In Broadcom’s high-availability model that is a three-node cluster with a virtual IP address, kept on separate ESX hosts by an anti-affinity rule. A single-node model has the smallest footprint, but recovers more slowly from a node failure and affects the management and control plane during upgrades14. The wizard marks the three-node deployment as recommended2. Its own schedule still sits inside the documented order for major and minor upgrades, which the lifecycle documentation sets separately for the management domain and for workload domains. Maintenance and patch releases need no strict order unless their release notes set one, and the 9.1.1 maintenance release does set component dependencies on the same page13.

Our recommendation is a dedicated manager when the domain must be upgraded on its own schedule, or when its network administration, change control or compliance scope must be separate. Sharing fits domains with separate administrative or identity boundaries that can follow each other’s upgrade timing and versions under one network operations team.

New cluster
Domain, shared NSX
Domain, dedicated NSX
Hosts
New cluster: New hosts and capacity in an existing domain
Domain, shared NSX: Dedicated ESX hosts
Domain, dedicated NSX: Dedicated ESX hosts
vCenter and SSO
New cluster: Shares the domain’s
Domain, shared NSX: Own vCenter and SSO domain
Domain, dedicated NSX: Own vCenter and SSO domain
NSX Manager
New cluster: Shares the domain’s
Domain, shared NSX: Shared with other domains, in 9.1 it can be the management domain’s
Domain, dedicated NSX: Own cluster, three nodes and a virtual IP in the high-availability model
Upgrades
New cluster: Tied to the domain’s vCenter, SSO and NSX Manager
Domain, shared NSX: NSX, vCenter and ESX upgraded in every domain on the shared instance
Domain, dedicated NSX: On its own schedule, within the documented upgrade order
Adds to the management domain
New cluster: Nothing, it uses the domain’s existing vCenter and NSX Manager
Domain, shared NSX: One more vCenter
Domain, dedicated NSX: One more vCenter and an NSX Manager cluster
Figure 1. What each option shares and what it adds.

When a domain is not enough

Workload domains in one instance still share its SDDC Manager and its management domain1, and each uses the VCF Identity Broker that serves its scope. One broker for the whole fleet has the lowest resource footprint but a large blast radius and reduced availability, while one broker per VCF Instance limits an authentication failure to that instance15.

If instance-level management (SDDC Manager, management vCenter and NSX) must fail independently, or you need disaster recovery to another region, the decision moves up to VCF Instances and the fleet deployment models, where the disaster recovery design adds a second instance in a separate availability zone or region16. A second instance still depends on VCF Operations and VCF Automation in the first instance1, and on a fleet-wide identity broker if one is used15. Two availability zones alone call for neither another instance nor a second workload domain: a stretched cluster, one of the cluster models above, keeps both zones inside one domain, though layer 3 multi-rack clusters cannot be stretched3. The zones need low-latency, high-bandwidth connectivity between them and stretched layer 2 networks or advanced routing16. The stretched cluster article sets out the order of stretching management and workload domain clusters.

What the domain wizard expects

A domain with a cluster needs hosts commissioned with the principal storage type it will use, each with at least one physical NIC connected to a standard switch. If the management domain hosts carry an express patch, the new hosts must be imaged with the same one. On vSAN, each host needs SSD or NVMe disks without existing partitions, and a vSphere Lifecycle Manager image must already exist in the VCF image library. vVols needs a VASA provider in the inventory and has been deprecated since 9.02.

The rest is addressing: a network pool with free IP addresses, DNS records for the new vCenter and NSX Manager, and a static IP pool or DHCP on the host overlay (TEP) VLAN, which from 9.1.1 a VLAN-backed VPC domain does not need. Full Stack VPC with distributed connectivity also needs an IP address and FQDN for one Virtual Network Appliance, or two of each for a cluster of them2. The VLAN-backed VPC model that NSX 9.1.1 introduces under the Distributed Transit Gateway works without TEPs: all traffic runs directly on physical VLANs, and private subnets are not supported7.

The dual-stack option appears only when SDDC Manager itself runs dual-stack, all hosts of the new cluster must use the same IP version configuration, the NSX overlay stays IPv4-only and needs a dedicated IPv4 range in the network pool, and vSAN and vMotion can run on IPv6 alone2.

The domain name, 3 to 20 characters, is used to generate object names such as distributed switch names, so Broadcom suggests including the location in it. The SSO domain name you enter creates a workload domain isolated from the other workload domains in the instance. vSphere Supervisor is enabled by default but can be deactivated. When enabled, it creates a Supervisor with NSX VPC networking, a single control plane VM and a single vSphere zone. Leaving it on adds inputs to plan: a Service CIDR for Kubernetes services that must not overlap any Supervisor-routable network, a control plane IP range of at least five addresses, and, with distributed connectivity, the FQDN of at least one Virtual Network Appliance. With centralized connectivity, Supervisor activation also needs an NSX Edge cluster with a tier-0 gateway deployed after the domain, unless an existing NSX Manager instance has a compatible one2. Our recommendation is to leave Supervisor on only for a domain that will run Supervisor workloads.

The “domain infrastructure only” option deploys the domain’s vCenter in the management domain together with a new NSX Manager instance or a joined existing one, and needs no unassigned hosts2, but nothing in that domain can be patched or upgraded until a cluster is added, and neither can any workload domain that shares its NSX Manager17.

Checklist and hold criteria

Our recommendation is to collect this evidence before the wizard opens, in the order of Figure 2.

  • Platform architect: the instance question. Evidence: the recovery requirement for management and for the workloads, showing whether either needs another region16.
  • Security and operations owners: the boundary. Evidence: a written yes or no for own vCenter or NSX administrators with no authority over the existing workloads, own identity provider, own upgrade schedule (for example an application certification or a change freeze), separate network change control and separate compliance scope, with the reason each domain exists. Ordinary delegation needs no domain, because vCenter grants a role on a selected object such as a cluster, and the permission can propagate to child objects18, so a role tested on a cluster is the evidence for a no.
  • Automation architect: network consumption. Evidence: which organizations or tools will create networks in the domain, with no consumer outside VCF Automation in a domain that VCF Automation uses, and any region spanning domains411.
  • Network architect: the NSX Manager choice. Evidence: the upgrade group and accepted failure domain of every domain on a shared instance, its IPv4 or dual-stack mode, and the vCenter and ESX versions of attached domains against the pinned states2813.
  • VI administrator: management domain capacity. Evidence: room on the primary cluster for another vCenter and, for a dedicated manager, one or three NSX Manager nodes kept apart by the anti-affinity rule2814.
  • VI administrator: hosts and image. Evidence: hosts commissioned with the principal storage type, the express patch level matching the management domain, unpartitioned vSAN disks and the vSphere Lifecycle Manager image in the library2.
  • Network engineer: addressing. Evidence: free network pool addresses, DNS records for vCenter and NSX Manager, the TEP pool or DHCP scope unless the domain is VLAN-backed, and Virtual Network Appliance IP addresses and FQDNs, only for Full Stack VPC with distributed connectivity2.
  • Platform engineer: Supervisor. Evidence: either Supervisor deactivated, or a non-overlapping Service CIDR, five control plane addresses and, for centralized connectivity, the Edge cluster plan2.
  • VI administrator: a domain without a cluster. Evidence: a date for its first cluster before the next patch window of every domain on its NSX Manager17.
Choosing where new workloads go in VCF 9.1Four questions in order. A: if management must fail independently or disaster recovery is needed in another region, plan another VCF Instance. Otherwise stay in this instance. Both continue to B. B: if the workloads need their own vCenter or NSX authority, identity provider, upgrade schedule, network change control or compliance scope, or have networks managed outside VCF Automation, plan a new workload domain and continue to C. Otherwise add a cluster to an existing workload domain and stop. C: separate NSX administration, upgrade timing, network change control or compliance scope, with no VCF Automation region spanning domains, means a dedicated NSX Manager cluster. Otherwise share an existing NSX Manager cluster, which in 9.1 can be the management domain one. D: if the management domain has room for another vCenter and any new NSX Manager cluster, create the workload domain. Otherwise expand the management domain first, then create it.AMust management failindependently, or is disasterrecovery needed in another region?YesNew VCF Instancefleet deploymentmodelNoBOwn vCenter or NSX authority,identity provider, upgradeschedule, network change control,compliance scope, or networksmanaged outside VCF Automation?NoAdd a cluster toan existingworkload domainYes: new workload domainCSeparate NSX administration,upgrade timing, network changecontrol or compliance scope,with no VCF Automation regionspanning domains?YesNoDedicatedNSX Manager clusterShared NSX Managercluster, can bethe managementdomain'sDRoom in the management domainfor another vCenter and any newNSX Manager cluster?YesCreate theworkload domainNoExpand the management domain Choosing where new workloads go in VCF 9.1Four questions in order. A: if management must fail independently or disaster recovery is needed in another region, plan another VCF Instance. Otherwise stay in this instance. Both continue to B. B: if the workloads need their own vCenter or NSX authority, identity provider, upgrade schedule, network change control or compliance scope, or have networks managed outside VCF Automation, plan a new workload domain and continue to C. Otherwise add a cluster to an existing workload domain and stop. C: separate NSX administration, upgrade timing, network change control or compliance scope, with no VCF Automation region spanning domains, means a dedicated NSX Manager cluster. Otherwise share an existing NSX Manager cluster, which in 9.1 can be the management domain one. D: if the management domain has room for another vCenter and any new NSX Manager cluster, create the workload domain. Otherwise expand the management domain first, then create it.AMust management failindependently, or is disasterrecovery needed in anotherregion?YesNoNew VCFInstanceStay in thisinstanceBOwn vCenter or NSXauthority, identity provider,upgrade schedule, networkchange control, compliancescope, or networks managedoutside VCF Automation?YesNoNewworkloaddomainAdd a clusterto an existingworkload domainCSeparate NSXadministration, upgradetiming, network changecontrol or compliance scope,with no VCF Automationregion spanning domains?YesNoDedicatedNSX ManagerclusterShared NSXManager cluster,can be themanagementdomain’sDRoom in the managementdomain for another vCenterand any new NSX Managercluster?NoExpand themanagementdomainYesCreate the workload domain
Figure 2. Four questions decide where new workloads go: instance, workload domain, NSX Manager cluster and management domain capacity.

Our recommendation is to hold the wizard while any item lacks its evidence. The safe stopping point is the unsubmitted wizard, with nothing deployed. A missing instance or boundary answer holds the design itself, and a retry needs the signed answers. A missing consumption, NSX or capacity record holds the domain, and a retry needs that record, or the management domain expansion completed when capacity was the reason. Host, addressing or Supervisor gaps hold only the submission, and a retry needs the corrected checklist evidence and the wizard validation passing. The creation task completing in Fleet Management is the acceptance evidence. A domain without a cluster and without a first-cluster date also holds the submission, and a retry needs that date agreed with the owners of every domain on its NSX Manager. Once created, it stops there, and the hold on patching for its NSX Manager group lifts once its first cluster is added.

Open points: the 9.1 taxonomy page lists a switch per cluster while the 9.1.1 pages allow later clusters to share one, and no page checked covers moving the clusters of an existing domain, or of one created before 9.1.1, onto one switch, or moving a domain to another NSX instance. The networking advice against mixed consumption also sits beside Mixed Tenancy Mode, which KB 444058 documents for VM Apps and All Apps organizations sharing one vCenter and NSX Local Manager, with the VM Apps organization configured first. Until Broadcom documents these cases, our recommendation is to give clusters in domains created before 9.1.1 their own switch, to treat the NSX choice as permanent, and to keep VCF Automation organizations of different types in separate workload domains unless Broadcom confirms in writing that the networking advice does not apply to Mixed Tenancy.

Our recommendation is to start from the smallest number of workload domains that meets the real separation requirements, and to record the owners’ answers as the reason each domain exists. The limit of 40 is not a reason to add one: each domain adds a vCenter to the management domain, plus credentials and upgrade work, for the life of the platform.

Sources

Show all 18 sources
  1. VCF Taxonomy
  2. Create a New Workload Domain
  3. vSphere Cluster Models
  4. Understanding Supervisors, Regions, vSphere Zones, vSphere Namespaces, & Classes
  5. VMware Cloud Foundation 9.1.1.0 Release Notes
  6. Distributed Switch Models
  7. NSX 9.1.1.0 Release Notes
  8. VCF Domain Models
  9. Workload Domain Models
  10. Tenancy Deployment Model 3: Centralized Management with Dedicated Workload Domains per Organization in a VCF Instance
  11. Centralized Connectivity Model
  12. VCF Taxonomy
  13. Lifecycle Management of VCF Components
  14. NSX Manager and Control Plane Models
  15. Identity Broker Models
  16. VCF Fleet Deployment Models
  17. What’s New in VCF 9.1: VCF Operations
  18. Understanding Authorization in vSphere