A VCF 5.2 instance reaches 9.1 by an in-place upgrade with a fixed component order. Eligible 5.2.x builds go straight to 9.1.1, while the SDDC Manager release notes send 5.2.1 through 5.2.2 or 5.2.3 first12. Only the fleet-level components and the management domain have to reach 9.1 in the first project, and workload domains can follow later as Day-N work1. The target is VCF 9.1.1 at its newest patches, numbered per component: SDDC Manager 9.1.1.02002, VCF Operations and its license server 9.1.1.01003, the fleet lifecycle, SDDC lifecycle and software depot components 9.1.1.02004, vCenter, ESX and NSX 9.1.1.0100567, all of October 12, 2026, and vSAN File Services 9.1.1.0200 of October 26, 20268. Pin each component from its own release notes rather than from a common suffix.
Most of the time goes into preparation: licensing, addresses for the new management services, hardware and identity. A plain vSphere 8 environment without SDDC Manager is converged instead, as in Converging existing vSphere and NSX into VCF 9.1, and staged as in From vSphere 8 to VCF 9.1.
Which 5.2 build goes where
From VCF 5.2.x the upgrade to 9.1.x can be sequential or skip-level. A platform older than 5.2 first brings the management domain and all workload domains to 5.2.x, and the jump to 9.1.1 needs no stop at 9.1.01. For VCF 5.1.x, KB 451166 names a second option: the management domain and all workload domains move to 5.2.x or to 9.0.x, and the upgrade to 9.1 starts from there. The 9.0.x stop is closed to Aria Operations 8.18.6 and 8.18.7: KB 438994 calls their upgrade to VCF Operations 9.0.x explicitly unsupported. The 9.1.1 release notes accept 5.2.x and 9.0.x sources released before 9.1.1 and start with VCF Operations 9.1.19. The build-specific rule in the SDDC Manager notes still applies.
A component can be upgraded only to a target released after its current version, the rule covers every component in the source bill of materials, and a patch release is a valid target only when its parent maintenance release is one1. VCF 5.2.4, released on May 27, 2026, therefore cannot go to 9.1.0, which the release notes date May 12, 2026, but can go to 9.1.1 of September 3, 2026110. KB 447234 from July, written when no 9.1.0.x release accepted SDDC Manager 5.2.4.0, is historical guidance for those targets. KB 450972 notes that the Interoperability Matrix shows patch-level paths only with Hide Patch Releases cleared.
For 5.2.1, the two Broadcom sources differ only on the direct route. The SDDC Manager 9.1.1.0200 release notes name 5.2.1 and require the hop through 5.2.2 or 5.2.3 before 9.1.1.02002. The Interoperability Matrix upgrade view for SDDC Manager, with patch releases shown, lists 5.2.1, 5.2.1.1 and 5.2.1.2 as compatible with 5.2.3 and with 9.1.1.0200, and 5.2.3 as compatible with 9.1.1.020011. A route through 5.2.3, the newer of the two named releases, meets both sources. Our recommendation is to take it for 5.2.1 and its patch builds alike, as its own change.
NSX 4.1.x has no single hop to 9.1, because VCF lifecycle management requires NSX 4.2 as its minimum baseline (KB 449282). Aria Operations has to be at 8.18.6 or later for a 9.1.1.x target12, and KB 455088 adds that 8.18.7 goes only to VCF Operations 9.1.1.0 or later, since older targets can leave the cluster inoperable.
Gates to clear before the first change
The new VCF management services are the largest network change in this upgrade and arrive midway, after VCF Operations and SDDC Manager both reach 9.1.x. The services runtime needs at least 12 IP addresses as a /28, and 30 as a /27 are recommended. Its internal block 198.18.0.0/15 must not overlap any infrastructure network, and from 9.1.1 the UI can switch it to 240.0.0.0/15 or 250.0.0.0/15. Three FQDNs cover the runtime, the fleet component and the instance component, and the identity broker and license server get one each, all on unique addresses outside the runtime range. The page rejects .local names and capital letters and requires a cloud proxy in the instance that hosts VCF Operations. Where the environment has additional management components, an SSL-terminating proxy configured in VCF Operations has to be removed first. With a 9.1.1 target the UI can choose the deployment network, and the API can use a VLAN-backed network when the management network is short of addresses13. KB 440630 adds that the license server needs DNS A and PTR records. The runtime size sets the size of every management service, so reserve that capacity in the management domain early.
Several core-component prerequisites are projects of their own14:
- A temporary IP address from the management subnet for each vCenter upgrade, reusable between them. From 5.2.x the domain plan offers only the vCenter reduced downtime upgrade15.
- No vCenter joined to an Active Directory domain. KB 373004 explains that VCF 9 removes direct AD join and Integrated Windows Authentication, so identity moves to LDAPS or federation first, a design covered in Identity and single sign-on design in VCF 9.1.
- No expired or expiring passwords or certificates, no failed workflows, no SDDC Manager resources in an activating or error state, and no active alarms on hosts or clusters. Failed workflows or error states mean a call to Broadcom Support before starting.
- Hosts that use their TPM modules on the latest TPM 2.0 firmware, and TPM modules that are not in use disabled in the BIOS. Before a TPM is disabled, KB 410791, written for Dell iDRAC, has the administrator confirm that the host’s encryption mode is not set to TPM.
- ESX hardware compatible with the target, and a manually updated vSAN HCL database (KB 315556).
Hardware deserves the longest lead time. KB 443586 warns that hardware supported on ESXi 8.0 is not automatically supported on ESX 9 and singles out I/O controllers and NVMe devices. Under KB 391170, end-of-life devices are not claimed by ESX 9.0 and an upgrade from the previous release may fail, and KB 428874 lists servers marked “VCF Supported. Confirm w/Vendor”, where BIOS and firmware support is the OEM’s responsibility.
Three blockers come from 9.1 itself. Active IPFIX on uplink port groups or LACP ports blocks the vCenter upgrade, and vCenter 9.1 refuses syslog on port 514 and expects 1514 with TLS16. KB 448668 describes a precheck that blocks the vCenter upgrade while the vCenter file-based backup points at SDDC Manager, so the backup target moves to an external server before the window. KB 455737 asks for its Update Manager database check, VUM_DB_Inconsistency_Checker.sql, and any correction it calls for, before a vCenter 8.0 U3 or 9.0.x is upgraded to 9.1 or 9.1.1.
Licensing, binaries and recovery points
Version 9 does not use upgraded keys. KB 282428 states that the Support Portal has no license key upgrade path for VCF 9, because version 9 is licensed through license files in the VCF Business Services console. For a 5.2.x source, licensing happens after the management services are deployed, by registering VCF Operations and the license server with that console1317. Components still below version 9 keep their license keys unchanged18. Version coexistence under one vCenter, including ESXi 8.x hosts that draw on version 9 capacity, is set out in VCF and vSphere Foundation licenses in one environment.
VCF Operations works in evaluation mode for up to 90 days after the upgrade, and registration and licensing have to happen within that period17. Each upgraded vCenter runs in evaluation mode for up to 90 days and needs a primary license with enough capacity for the product it will run18. KB 455974 shows the end state of a missed deadline: hosts disconnect from vCenter, and virtual machines can no longer be powered on or off, while running ones keep running. KB 437242 lists a purchased subscription eligible for version 9 as a licensing prerequisite. Treat that subscription, visible in the Business Services console, as a gate before the first change. A second gate comes before the ESX stage: a registered license server and a licensed vCenter. KB 453417 shows the ESX precheck failing with “The current vCenter is not licensed by a license server” while the license server is not registered, and KB 446155 adds that hosts provisioned by Auto Deploy with stateless caching get no 90-day evaluation, so their vCenter has to be licensed before they are upgraded. After go-live the license file keeps a rolling 180-day validity that is renewed by reporting usage (KB 448518), which needs an owner in operations.
The SDDC Manager upgrade bundles are downloaded the 5.2 way or with the VCF Download Tool, together with the management services and license server binaries. Once SDDC Manager is on 9.1, an online depot is reconfigured to authenticate with an activation code from the Business Services console instead of a download token19. After the management services are deployed, the fleet-level software depot has to be configured before the remaining components can be upgraded13, and the release notes ask for the latest available binaries at every step9. Depot modes are compared in Lifecycle management in VCF 9.1.
Before SDDC Manager, the procedure asks for a recent SDDC Manager backup to an external SFTP server, a snapshot of the appliance, recent backups of the components it manages and resolved prechecks19. Before the core components, it asks for backups of SDDC Manager and every vCenter and NSX Manager, plus a cold snapshot of SDDC Manager14. Per the backup methods table, SDDC Manager and vCenter take file-based or image-based backups, NSX Manager file-based backups only, with the Edge configuration inside the NSX Manager backup20. KB 312592 states that snapshots of NSX Manager, Global Manager and Edge appliances are not supported. Under NSX Federation, Global Manager backups run on the active Global Manager only (KB 390887). The NSX backup holds configuration, not Edge VMs, so a lost Edge is redeployed (KB 411895). Restoring the pre-upgrade NSX 4.2 backup needs a new NSX Manager. KB 417758 asks for the exact version and the backup’s FQDN or IP address, with a different IP only when the published FQDN resolves to it in DNS, and for the same FQDN publishing and IP stack. KB 373896 asks for the same FQDN and IP address and the same version and build. Our recommendation is to deploy it with the same FQDN and the same IP address, on the exact version and build, with the same FQDN publishing setting and IP stack. The restore also needs the passphrase that encrypted the backup21. Every VCF Operations node gets a snapshot before its upgrade22, and KB 342576 takes the whole cluster offline first, snapshots all nodes including cloud proxies without memory or guest quiescing, and warns that snapshots kept beyond 72 hours degrade performance. KB 405275 ends each 4.x and 5.x upgrade with a health check and a full backup, so the intermediate 5.2.3 change for 5.2.1 ends that way too. A failed component shows its reason and remediation steps and is retried once they are resolved23. The upgrade guide documents no rollback of the platform as a whole1, so these backups are the recovery path, and each needs a named owner and a tested restore before its window.
Two points in the order are documented places to stop. Once the management domain is complete, the workload domains may wait, and each workload domain is upgraded on its own schedule after that1. The sequential domain plan also gives NSX Manager and vCenter separate windows15.
The management-plane stages
The order in the upgrade guide’s 5.2 table is a requirement. The fleet stages run in the first VCF Instance: Aria Operations and its cloud proxy become VCF Operations 9.1, then vSphere Replication, VMware Live Site Recovery, vSAN Data Protection and Avi Load Balancer 32.1.1 follow where deployed, and then SDDC Manager. The management services and license server come next, with the identity broker deployed as part of them, followed by Aria Automation, Aria Automation Orchestrator, Aria Operations for Networks, log management and HCX1.
From 8.x, VCF Operations is upgraded only with a PAK file12. The primary instance must have a cloud proxy, and an 8.18.x cloud proxy outside the first instance that collects logs for Aria Operations for Logs with a one-time key is shut down after the upgrade and replaced. Cloud proxies collect no data while they upgrade, and VCF Operations then leaves its Aria Suite Lifecycle environment without its VM being deleted24.
SDDC Manager is upgraded from the 5.2 SDDC Manager UI, through Plan Upgrade on the management domain19. HCX needs coordination beyond the instance: after HCX reaches 9.1.x, every paired appliance has to move to 9.0 or later, because pairing between 9.0 and earlier versions breaks1.
What happens to each Aria product
Aria Suite Lifecycle and VMware Identity Manager have no upgrade to 9.1, and both stay in service while Identity Manager is an authentication source for VCF Automation 9.11. Once VCF Automation authentication has moved off Identity Manager through the documented migration, the two are no longer required for the operation of VCF Automation25. The Automation detail is in From Aria Automation to VCF Automation 9.1.
Aria Operations for Networks 6.14.0 Patch 6, 6.14.1 or later is imported into VCF Operations and upgraded from there, and only one instance can be imported26. KB 440630 adds that Operations for Networks can no longer be upgraded through its own UI. With several instances, the one to import is a choice, and every other instance needs its own plan.
Aria Operations for Logs 8.x has no upgrade path to log management 9.1. Log management is deployed with a new FQDN on the network that hosts the management services, not on a custom NSX overlay, and the 8.x configuration is migrated2728. The link to the old cluster is made in that upgrade workflow and expires 90 days later, after which old logs can no longer be searched from VCF Operations29. Those queries reach the old cluster, so it has to keep running for them. The documentation allows the legacy appliances to be shut down once the post-upgrade configuration is complete28. Keeping them until the 90 days end is the safer plan. Agents, data transfer and archives are covered in Log management in VCF 9.1.
Core components in each domain
The domain stages follow the fleet stages: NSX Global Manager where NSX is federated, NSX Manager and vCenter, the vSphere Kubernetes Service to 3.6.0 or later and then the Supervisor, the vSAN witness host, ESX, the NSX Edge cluster with NSX finalize, the distributed switch, VMware Tools 13.1, virtual machine compatibility, the vSAN on-disk format and vSAN File Service1. vSAN File Services 9.1.1.0200 replaces all earlier 9.1.x releases of it8. The management domain sequence also includes the move from vSphere Lifecycle Manager baselines to images before ESX, and ends with the VCF configuration upgrades30.
In 9.1, NSX Manager and vCenter share one step of the domain plan. The optimized maintenance window option runs the reduced downtime preparation of vCenter without downtime, then upgrades the NSX Manager nodes and switches vCenter over in a single window. It requires the vCenter target version to equal the current SDDC Manager version. The sequential option gives each component its own window, NSX Manager first. Either way the plan steps run in order, and the NSX Edge cluster and NSX finalize come after the ESX hosts15.
A workload domain at 5.2 or later repeats a shorter set of the same steps, ending with the distributed switch and the vSAN on-disk format. When all upgrades have succeeded, the VM snapshots taken beforehand are removed and the newly installed components backed up31.
Running 9.1 management over 5.x workload domains
A 9.1 management domain can manage workload domains at 5.x, 9.0 and 9.118. The upgrade starts with the instance that hosts VCF Operations, the management domains of the other instances follow, and each workload domain can be upgraded at any time after its own instance’s management domain1.
Broadcom’s Product Lifecycle lists end of service on October 11, 2027, for the VCF 5.2 releases and on August 12, 2028, for VCF 9.1.0 and 9.1.132. The listing is per release, so a 5.x workload domain left under a 9.1 management domain would still fall under the 5.2 date. Planned that way, the last wave finishes before October 11, 2027, with room for a failed window.
Close each wave with evidence rather than a status change: post-upgrade validation tests passed, the pre-upgrade snapshots removed and fresh backups of the new components taken. The project ends when the old Logs appliances are shut down and, where nothing but VCF Automation used them, Identity Manager and Suite Lifecycle are retired after the authentication migration. Put those two decommissioning dates in the change calendar on the day the first window is booked.
Sources
Show all 32 sources
- Upgrading to VMware Cloud Foundation 9.1.x
- VCF Installer / SDDC Manager 9.1.1.0200 Release Notes
- VCF Operations 9.1.1.0100 Release Notes
- VCF Operations Patch Releases 9.1.1.0200: Fleet Lifecycle, SDDC Lifecycle and Software Depot
- vCenter 9.1.1.0100 Release Notes
- ESX 9.1.1.0100 Release Notes
- NSX 9.1.1.0100 Release Notes
- vSAN File Services 9.1.1.0200 Release Notes
- VMware Cloud Foundation 9.1.1.0 Release Notes
- VMware Cloud Foundation 9.1 Release Notes
- Broadcom Product Interoperability Matrix: Upgrade Path
- Upgrade VCF Operations to 9.1
- Deploy VCF Management Services and License Server for the VCF Upgrade
- Prerequisites for Upgrading the VCF Core Components
- Plan a Domain Upgrade to 9.1
- VCF 9.1 Product Support Notes
- Registering VCF Operations and a License Server with the VCF Business Services Console
- Mixed-Version Environments
- Upgrade SDDC Manager to 9.1
- Component Backup and Restore of VMware Cloud Foundation
- Restore a Backup (VMware NSX 4.2)
- Create Snapshots of the VCF Operations Nodes Before You Upgrade
- Monitoring VMware Cloud Foundation Upgrades
- Upgrading to VCF Operations 9.1
- Migrate VCF Automation Authentication from VMware Identity Manager to VCF Identity Broker
- Upgrading to VCF Operations for Networks 9.1
- Upgrading to Log Management 9.1
- Deploy Log Management
- Log Partitions and Searching Older Partitions
- Upgrade the Remaining Components in the Management Domain to 9.1
- Upgrading VMware Cloud Foundation Workload Domains to 9.1.x
- Broadcom Product Lifecycle