Three choices in a vSphere Foundation 9.1 cluster design are one-way. The principal storage type picked in the VCF Installer for the first cluster cannot be changed1. Stateless provisioning can be activated only while a cluster is empty, after which the cluster takes stateless hosts only and cannot use vSphere Configuration Profiles2. Configuration Profiles cannot be deactivated once enabled, and a switch from host profiles to them is irreversible3. A cluster’s image components and its compute policies can still be added, modified or deleted later45. The baseline is vSphere Foundation 9.1.1 with the October 12, 2026, patches. Its vCenter 9.1.1.0 brought DRAM-aware admission control, VM-to-VM compute policies and an Auto Deploy fix6.
Our recommendation is a uniform first cluster of installed hosts, Configuration Profiles from creation on later clusters without stateless or DPU-backed hosts, and at least three hosts with room for one in maintenance wherever admission control runs.
vCenter and ESX are vSphere Foundation components7, and Broadcom’s 9.1.1 feature comparison of November 16, 2026, marks vSphere Lifecycle Manager, Configuration Profiles, Host Profiles, Auto Deploy, Zero Touch Provisioning (as vSphere elastic provisioning), HA, DRS and memory tiering for vSphere Foundation8.
The installer’s first cluster
The VCF Installer deploys vSphere Foundation only together with the VCF management services, and a platform without them is deployed by hand1. They can be deployed on the management vCenter7. The wizard builds that vCenter with one cluster and offers three principal storage types for it: vSAN (ESA or OSA), VMFS on Fibre Channel and NFS v3. A Fibre Channel datastore must already be created and mounted on all hosts. An NFS v3 server must already exist and meet the vSphere NFS guidelines, and if the installer runs on one of the future hosts, the datastore must be mounted there too. Clusters with a different principal storage type can be added later. Once deployed, the management services VMs must stay in their resource pool and folder, since moving them makes later patching, deployment and scale-out operations fail1.
The installer has no option for iSCSI, FCoE, NVMe or NFS 4.11, yet the comparison marks VMFS over iSCSI, FCoE, NVMe/FC, NVMe/TCP and NVMe/RDMA, and NFS 4.1, for vSphere Foundation with no qualifier. In the VCF columns the same rows are marked supplemental, and only Fibre Channel and NFS v3 may be principal8. The vSphere Foundation installer page does not use the term, so our recommendation is to add such datastores in vCenter once the installer has built the cluster on one of its three types.
Broadcom’s vSphere Foundation 9.1 FAQ says vSAN need not be enabled in every cluster: the 0.25 TiB of raw vSAN capacity per licensed core is pooled, so compute-only clusters can pass their unused capacity to vSAN clusters9.
A second vCenter brings up Enhanced Linked Mode. KB 436518 says vSphere Foundation 9 does not need it broken, as it remains the way to link vCenter instances for single sign-on. KB 436011 calls it deprecated from vCenter 9.0 and gives the steps to break it, after powered-off vCenter snapshots, and link the instances in VCF Operations instead, with identity provider permissions then set on each vCenter.
Images and Configuration Profiles
A vSphere Lifecycle Manager image is exact: after remediation no deviation from it is possible, and other solutions cannot push VIBs to the hosts. An image can be exported and imported, as JSON, in another vCenter, whereas baselines cannot leave theirs. ESX live patching and DPU-backed hosts need images4. With several workload vCenters, our recommendation is to export the image once and import it in each, after loading the components it names into each depot, since the JSON holds only metadata, according to a KB written for vCenter 8.0 and later (KB 367798).
vSphere Configuration Profiles keeps a cluster’s desired host configuration, checks compliance and remediates drift, on clusters managed with images or baselines, from vCenter 9.0. It manages distributed switch configuration and, in vSphere Foundation 9.1, can be enabled on a vSAN cluster to manage vSAN settings and show their drift, for single-site vSAN only: stretched cluster settings stay outside it even when the profile reports Compliant (KB 451902). It cannot be enabled on a cluster with DPU-backed hosts. Host profiles were announced deprecated in vSphere Foundation 9.03.
Stateless hosts keep a cluster out of Configuration Profiles2, and with it out of both documented routes to memory tiering: cluster-level activation in Configuration Manager, part of Configuration Profiles, and per-host activation with ESXCLI, which needs a cluster managed by a single image and Configuration Profiles10. For a cluster created in vCenter without stateless or DPU-backed hosts, our recommendation is to enable Configuration Profiles at creation3 rather than start with deprecated host profiles and migrate one way later. The installer’s wizard does not mention it, but it can be enabled on that cluster afterward13.
Installed, stateless or Zero Touch hosts
The wizard points to a preparation page for both products1, which says VMware Cloud Foundation does not support stateless ESX hosts and installs ESX from an ISO image11. The lifecycle documentation covers stateless hosts, Auto Deploy and Zero Touch Provisioning (ZTP) for vSphere Foundation 9.12.
On hardware, the preparation page says VCF does not support heterogeneous clusters during the initial management domain deployment, because vCenter does not exist yet, and that all management domain hosts must come from one hardware vendor, a rule that names no product11. For vSphere Foundation 9.1 the lifecycle documentation describes mixed clusters: Auto Deploy rules can give stateless hosts from different vendors different Image Builder images, one per vendor rather than a composite, and ZTP can remediate a heterogeneous cluster with a composite image2.
For the first cluster, our recommendation is to follow the installer, which treats it as the management domain1 and prepares its hosts from an ISO11: installed, uniform hosts, with stateless or ZTP provisioning and mixed hardware kept for later clusters.
For later clusters, stateless Auto Deploy, documented from vCenter 9.0 with hosts at 8.0 or later, runs the cluster’s lifecycle from Auto Deploy alone, with the restrictions described at the start. Broadcom says Auto Deploy hosts with stateless caching get no evaluation period and asks for vCenter to be licensed first (KB 446155). Auto Deploy stateful, which needs vCenter 9.1 or later and is the default for new clusters, stores the image on the host and works with Configuration Profiles, but takes no composite image, and it can change to stateless only while the cluster is empty. ZTP needs vCenter and ESX 9.1 or later. Hosts boot over UEFI HTTP or HTTPS, HTTPS recommended, from a single vCenter URL on port 443. ZTP accepts single or composite images and works with Configuration Profiles, and a ZTP cluster can later move to Auto Deploy stateful while it is empty or already holds stateful hosts2. Only ZTP combines composite images with Configuration Profiles, so our recommendation is ZTP for a cluster mixing server vendors that should keep them, and stateful Auto Deploy for clusters whose hosts share one vendor image.
vCenter 9.1.1.0 fixes a timing conflict between distributed switch configuration and Auto Deploy that could make stateful Auto Deploy hosts fail to deploy with a “Certificate path is missing” error when a host profile adds them to a distributed switch6.
Host count, failover reserve and memory tiering
The host preparation page says the number depends on storage type and deployment model and points to the VCF Installer’s planning section or the Planning and Preparation Workbook11. vSphere sets one floor of its own: HA admission control needs at least three hosts in the cluster12, so our recommendation is three hosts as the minimum for any cluster that keeps it on.
Admission control reserves failover capacity as a percentage of cluster resources, a slot policy or dedicated failover hosts. Broadcom says never to deactivate it permanently, since nothing then assures that VMs restart after a failure, yet also to switch it off temporarily so that vMotion can evacuate hosts during remediation. In a two-node cluster that leaves practically no HA guarantee, because once one host is in maintenance mode vCenter cannot fail virtual machines over to it12. Our recommendation is to size each cluster to carry its load with one host in maintenance, or to record that remediation windows run without reserved failover capacity.
Memory tiering over NVMe fits hosts whose active memory has not exceeded 50 percent of DRAM at any point, Broadcom’s condition for optimal performance13. Up to vSphere 9.1, admission control counted DRAM and NVMe as one pool, so a tiered cluster could show green status and still fail to restart VMs after a host failure, because a VM cannot power on from NVMe, and no alert flagged the shortfall. From 9.1.1, admission control checks DRAM separately and reports a shortfall through the existing failover capacity alerts and status colors14. On a tiered cluster that has not reached 9.1.1, a green admission control status is no proof that its VMs will restart.
The 9.1 requirements list vCenter and ESX 9.1 or later and a local, mixed-use NVMe drive rated for at least 3 drive writes per day, not a configured vSAN cache or data disk. By default the tier is capped at the DRAM size, 1:1, up to 4 TB, and tiered hosts lose Quick Boot15. Broadcom advises against sharing one physical NVMe drive between tiering and vSAN and against memory overcommit while tiering is active. vMotion of a tiered VM takes 1.5 to 2 times longer, which lengthens remediation evacuations, and DRS handles clusters mixing tiered and non-tiered hosts16. The 50 percent condition is stated for normal operation, so our recommendation is to size a tiered cluster so that the surviving hosts stay under it after a host failure.
In 9.1.1, the cluster resource percentage policy in automatic mode reserves the DRAM of the n hosts with the most DRAM, n being the failover level. In manual mode the configured memory percentage applies to the cluster’s total DRAM, and that DRAM reservation counts within the total memory reservation, not on top of it. The dedicated failover hosts policy is DRAM-aware too. The slot policy is not, and Broadcom says not to use it with memory tiering14. Its HA best practices add that a dedicated failover host needs at least as much DRAM as the largest active host17. In automatic mode, one host with far more DRAM than its peers therefore raises the cluster’s DRAM reservation, and our recommendation is to give the hosts of a tiered cluster the same DRAM.
VM placement with compute policies
vCenter 9.1.1 adds VM-to-VM affinity and anti-affinity to compute policies, for ordinary VMs and VM Service VMs6. Compute policies select VMs and hosts through vSphere tags, the new types keep VMs together or apart per host, cluster or zone, and vCenter does not detect conflicts between policies5.
The vCenter 9.1.1 release notes say strictness set in the VM spec file can be required or preferred at initial placement, but only preferred is supported at runtime6. The DRS documentation says that from 9.1.1 DRS never violates a required policy, even in load balancing, maintenance mode and HA failover, while a preferred one can yield to a hard constraint18.
The DRS page advises against DRS rules and compute policies on the same non-VM Service VMs, since conflicting hard constraints leave no compatible host and placement fails with NoCompatibleHost18. A policy built on host tags needs enough tagged hosts to carry the workload while one of them is in maintenance or being replaced5.
Names and addresses
vSphere Foundation needs a unique FQDN and a static, unused IP address with forward and reverse DNS for every component, and the top-level domain label may contain ASCII letters only. vCenter, ESX hosts and VCF Operations work with a .local domain, while containerized services such as the VCF management services and the Supervisor do not19. KB 460245 describes DNS forwarding between a .local domain for the core appliances and an RFC-compliant one for those services. Each ESX host takes one FQDN, one vMotion address and, with vSAN, one vSAN address. vCenter, the VCF Operations primary node, the license server and the optional cloud proxy take one FQDN each, and the VCF management services one each for the fleet components, the instance components and the services runtime, written without capital letters19.
A four-host vSAN cluster with the management services and a cloud proxy needs eleven FQDNs and eight vMotion and vSAN addresses. The services runtime needs a pool of at least 10 node addresses on top, 30 recommended, and log management later takes six of those addresses19. The installer expects the names and addresses to be configured before it runs1.
Sign-off before hosts join
Our recommendation is to close these items before hosts join a cluster.
- First-cluster storage. Owner: storage team. Evidence: the type recorded as permanent, and the Fibre Channel datastore mounted on every host, the NFS v3 export meeting the guidelines, or vSAN devices on the compatibility list.
- First-cluster hosts. Owner: server team. Evidence: the host count from the installer’s planning section or the workbook, and ESX installed from an ISO on hosts of one vendor and hardware profile.
- Names and addresses. Owner: network team. Evidence: forward and reverse lookups for every FQDN, an RFC-compliant domain for the management services, vMotion and vSAN addresses per host, and 30 free runtime addresses, or 10 plus six for planned log management.
- Each later cluster. Owner: virtualization architect. Evidence: a record of provisioning method, image type and Configuration Profiles (never on DPU-backed hosts), versions meeting the method’s minimum, vCenter licensed before stateless hosts boot, vCenter 9.1.1.0 or later where a host profile joins stateful Auto Deploy hosts to a distributed switch, and the shared image imported in every vCenter with its components in each depot.
- Failover capacity. Owner: capacity planner. Evidence: three or more hosts where admission control runs, a calculation showing the load fits with one host in maintenance, and for tiered clusters vCenter 9.1.1 or later, the percentage or dedicated failover hosts policy, failover hosts with at least the largest active host’s DRAM, and active memory under half of DRAM on the surviving hosts.
- Placement policies. Owner: virtualization architect with application owners. Evidence: tags in place, no VM under both DRS rules and compute policies, enough tagged hosts with one in maintenance, and a failover test showing where anti-affinity VMs restart.
- Enhanced Linked Mode, with a second vCenter. Owner: identity owner. Evidence: the keep or break decision recorded and, before any break, powered-off snapshots of every linked vCenter.
Our recommendation is to hold each step while its items lack evidence. For the first cluster, the safe stopping point is the wizard’s validation step, before deployment, where you can go back to a page or re-upload a corrected JSON specification and re-run the validations1. Retry when the storage, host and DNS evidence exists and the validations pass. For a later cluster, the stopping point is the empty cluster without Configuration Profiles, where the provisioning method can still change2. Add hosts or enable Configuration Profiles once the cluster’s record is approved, its versions meet the minimum, vCenter is licensed before stateless hosts boot (KB 446155) and the shared image is imported in every vCenter with its components in each depot. A cluster failing the capacity item takes no production VMs until hosts are added or load moves, admission control shows green on vCenter 9.1.1 or later and, for tiered clusters, the DRAM calculation holds: a DRAM-aware policy, failover hosts with the largest active host’s DRAM, and surviving hosts under half of DRAM. Compute policies stay on test VMs until the tags are in place, no VM is under both DRS rules and compute policies, enough tagged hosts remain with one in maintenance, and the failover test shows the expected placement. Enhanced Linked Mode stays until the decision and the snapshots exist.
Several points remain open, each with our recommended action. The DRS and compute policy documentation disagree with the release notes on required strictness at runtime: design as if only preferred holds after placement, test anti-affinity through an HA failover, and confirm the behavior for your build with Broadcom Support. The two Enhanced Linked Mode KBs point different ways: keep the link until vCenter groups in VCF Operations are needed. The preparation page is silent on stateless hosts and mixed vendors in vSphere Foundation: keep the first cluster uniform. The HA page requires three hosts for admission control yet describes deactivating it to remediate a two-node cluster: size a two-node cluster so one host carries all its VMs. Tiering on stateless hosts through PowerCLI is not described: plan tiering only on clusters with Configuration Profiles.
Sources
Show all 19 sources
- Start a New vSphere Foundation Deployment by Using the VCF Installer Deployment Wizard
- Managing Hosts Provisioned with vSphere Auto Deploy or Zero Touch Provisioning
- What is vSphere Configuration Profiles
- What Is the Difference Between vSphere Lifecycle Manager Images and Baselines
- vSphere Compute Policies
- vCenter 9.1.1.0 Release Notes
- Components in VCF and vSphere Foundation
- VMware Cloud Foundation 9.1.1 and VMware vSphere Foundation 9.1.1: Feature Comparison & Upgrade Paths
- VMware vSphere Foundation 9.1 Frequently Asked Questions (FAQs)
- Memory Tiering Configuration
- Preparing ESX Hosts for VCF or vSphere Foundation
- vSphere HA Admission Control
- Capacity Planning Considerations
- Memory Tiering and HA Admission Control
- Memory Tiering over NVMe
- Memory Tiering Considerations and Best Practices
- Best Practices for vSphere High Availability Clusters
- DRS Rules and Compute Policy Interactions in vSphere